When a construction project lasts for months or years, the price of steel, cement or energy can move a great deal between the day you submit your bid and the day you buy the materials. Price revision is the mechanism that lets you adjust what you charge to reflect those changes. But it does not apply automatically or in every case: on public works it depends on the law and the tender specifications, and on private works, on what you have signed. This article explains when it applies, how it is calculated and what to check before signing.
On public works: when prices can be revised
Price revision in public sector contracts is covered by articles 103 to 105 of Ley 9/2017, de Contratos del Sector Público (Spain's Public Sector Contracts Act). The main points are these:
- Only periodic, predetermined revision (article 103.1): that is, using a formula set in advance, not on demand.
- Works contracts are among those that allow revision (article 103.2), once it has been justified in the contract file.
- It must be in the tender specifications. The contracting body decides whether to establish the right to revision and sets the formula (article 103.3), and the specific administrative clauses document must set it out in detail. The formula does not change during the life of the contract (article 103.4). If the specifications make no provision for revision, there is none.
- Some costs are never revised: depreciation, financial costs, overheads or structural costs and industrial profit (article 103.2).
The 20% threshold and the one year from formalisation
Article 103.5 establishes that, except in energy supply contracts, revision takes place once at least 20% of the contract value has been carried out and one year has passed since formalisation. As a result, the first 20% executed and whatever is executed in the first year fall outside revision.
This wording comes from Ley 11/2023, de 8 de mayo (Law 11/2023 of 8 May), which amended paragraphs 2 and 5 of article 103. Previously, the period was two years from formalisation. If you have older contracts or are reading documentation from before 2023, bear this change in mind and check which wording applies to your contract.
An example to illustrate: in a 24-month works contract with revision provided for in the specifications, the certifications for the first year are not revised; from then on, those that qualify are revised once 20% of the value has been executed.
How it is calculated: standard formulas and indices
Revision is carried out using a formula that weights the share of basic materials in the contract price and applies the change in their price indices. Article 103 provides for the Council of Ministers to approve standard formulas and, where they exist for a type of contract, the contracting body cannot set a different one.
- The standard formulas for works contracts are in Real Decreto 1359/2011, de 7 de octubre (Royal Decree 1359/2011 of 7 October), which approves the list of basic materials (cement, steel products, aggregates and rock, energy, ceramic materials, bituminous materials and others) and the formulas for each type of work. Labour is not part of them.
- The monthly indices for each material are produced by the Instituto Nacional de Estadística (Spain's National Statistics Institute) and approved by order of the Ministerio de Hacienda (Ministry of Finance) (article 103.8).
- The result is a coefficient applied to the net amounts of the work carried out that is eligible for revision (article 103.9).
- The amount is paid or deducted automatically in certifications or interim payments, and any discrepancies can be settled in the final certification or in the final settlement (article 105). Revision works in both directions: if the indices fall, so does the price.
- If the contractor is late through its own fault, the indices for the dates on which the work should have been carried out apply, unless those for the actual period give a lower coefficient (article 104).
Apart from this general regime, Real Decreto-ley 3/2022, de 1 de marzo (Royal Decree-law 3/2022 of 1 March), approved an exceptional revision for public works contracts affected by the rise in material prices, with its own requirements and deadlines and several later amendments. If you have contracts from that period, check with your adviser whether it applied to you.
On private works: whatever you have agreed
On private works there is no mandatory statutory formula. What the contract says governs, and if it says nothing the starting point is not very favourable to the contractor: article 1593 of the Código Civil (Spanish Civil Code) establishes that anyone who undertakes a job for a lump sum, according to a plan agreed with the owner, cannot ask for a price increase even if wages or materials have gone up, unless there is a change to the plan that increases the work and the owner has authorised it.
If the project is going to be long or material prices are volatile, it is worth including a revision clause. Some guidelines:
- Define what is revised: the whole price or only the materials with the greatest weight.
- Use objective indices, such as official material price indices, and state which one and its base date.
- Set a threshold and a period: for example, only changes above a certain percentage and only from a certain month.
- Make it symmetrical: if prices rise, the price rises; if they fall, it falls. The client will accept it more readily.
- Make clear how it is invoiced: in each certification or in a final settlement.
Before signing a works contract
- Read the specifications to see whether there is revision and with what formula. If there is not, your bid has to cover the risk of price rises.
- Work out how much of the contract falls outside revision (the first 20% and the first year) and how much material you will buy in that period.
- Consider buying or fixing prices with suppliers for the materials with the greatest weight.
- Keep track of progress on site: revision is applied to what has been executed in each period, and without properly dated certifications it cannot be calculated.
Well-kept certifications with Gestrab
Price revision is calculated on what has been executed and certified in each period, so the first thing is to have those figures clean and dated. In Gestrab each project distinguishes, item by item, the planned, completed, certified and invoiced quantities, the progress of each item is recorded on each date and certifications are invoiced cumulatively. You can find it in certifications and cumulative invoicing.
And because each purchase can be assigned to its project, you can see how material costs for each project have evolved against what you budgeted, as explained in costs per project.