A bathroom, a kitchen, a small roof or a new floor for a shop unit. Small renovation jobs bring in steady work, but many companies get the feeling that they work hard on them and earn little. That is usually true, and almost always for the same reasons: costs that are not quoted for, dead time that goes unseen and extras that are never charged. In this article you will find where the money leaks away and what to do at each stage to stop it.
Where the margin goes on a small renovation
On a large project, a lost day or an extra trip gets absorbed into the total. On a renovation lasting a few days, every unforeseen event weighs heavily. The usual leaks are these:
- Travel. Going there and back, parking, carrying materials up, taking rubble down. On a three-day renovation it can account for a significant share of the hours.
- Trips to the warehouse or the shop for a part that was missing.
- Waiting between trades. The tiler who cannot get in because the plumber has not finished.
- What turns up when you open things up. Pipes in poor condition, damaged floor slabs, installations that do not meet regulations.
- The "while you're here" jobs. Small jobs the client asks for as you go along and that nobody writes down.
- Finishing touches and snagging after handover, which force you to go back.
- The company's structure. The office, the vehicle or the insurance cost the same for one renovation as for another job, and they have to be spread across them.
Before you start: the quote
- Always visit the site. In renovations, quoting from photos is quoting blind.
- Quote by line item, with measurements and prices, not a single overall price. If something changes later, you will know which item is affected and by how much.
- Include what doesn't show: protection of communal areas, rubble removal, auxiliary equipment, final cleaning and travel.
- Make clear what the price does not include: anything that comes to light during demolition, material changes requested by the client or work by other trades.
- Set out how extras will be valued: at the prices in the quote itself, or by the hour plus materials, stating the hourly rate.
- Calculate with your real costs. Hourly cost including social security contributions, a share of overheads and travel time.
During the job: planning and work reports
On a small renovation, a day's delay is a large part of the job. Some practices that help:
- Plan the week using work orders for each crew, with the materials they need to take. Fewer trips to the warehouse.
- Group nearby jobs on the same day where possible, so that travel is shared.
- A daily work report with hours, materials and remarks, signed by the client. The hours spent on a renovation are forgotten very quickly.
- If an extra comes up, write it down. On a work report or on a separate line, with the client's approval before doing it if the amount warrants it.
- Photograph what turns up when you open things up before touching it. It is the best way to justify unplanned work.
At the end: invoice everything you have done
- Invoice as soon as the job is finished, not when you have time. The later the invoice arrives, the more it gets disputed.
- Invoice from the signed work reports, with extras kept separate from what was quoted.
- If the renovation lasts several weeks, agree stage payments based on progress: what has been completed on each item is invoiced without waiting for the end.
- Check that no delivery notes or work reports are left uninvoiced when you close the job.
- Do a snagging visit with the client before regarding the job as finished and put in writing what remains outstanding. That way you avoid going back again and again for details nobody had asked for.
A word on snagging: going back to a job that has already been invoiced costs the same as any other visit (travel, hours, sometimes materials) and brings in nothing. If it happens a lot with one type of work, it is a sign that something is wrong in the execution or the handover, and it is worth recording it as one more cost of that job so that you see it in the figures and not just in the diary.
Comparing planned and actual on each renovation
What really changes the figures in the medium term is closing each renovation by comparing what was quoted with what it actually cost, even if it only takes five minutes:
| Item | What to compare | What it tells you |
|---|---|---|
| Hours | Planned hours versus hours on the work reports | Whether your productivity rates are realistic |
| Materials | Planned versus used and purchased | Waste, short measurements or outdated prices |
| Travel | Actual days and kilometres | Whether you are charging for it or giving it away |
| Extras | Work done outside the quote and invoiced | How much goes unpaid |
| Margin | Invoiced minus total cost, including overheads | Whether that type of renovation is worth your while |
For example, if after ten bathroom renovations you see that every one has used more tiling hours than planned, the problem is not one job: it is the price you put on that item.
Renovations under control with Gestrab
With Gestrab you prepare the quote by line item, with its measurements, price and amount, and the job is generated from it. You plan it using work orders that reach each employee's mobile, and from each order the operative creates their work report with hours, vehicle, kilometres and materials, which the client signs on the mobile and receives by email. You can see it in quotes and jobs.
Costs are calculated per work report and per job: labour, materials, weighted overheads and travel shared across the day's work reports, which on small renovations makes all the difference. You can find it in job costing. And when invoicing, you can do it from the cumulative progress of the job or from the pending delivery notes generated by the work reports.