A job can look profitable if you only count what has been spent on it: wages, materials and the odd subcontractor. But the company also pays for the office, the yard, the foreman who moves from site to site, insurance, the van nobody gets assigned to, or software. If those costs are not allocated across your jobs, every one of them looks more profitable than it really is, and your quotes are built on a margin that does not exist. This article explains what indirect costs are, how to allocate them and which mistakes to avoid.
Direct costs, indirect costs and overheads
There is no single way to classify them, but in the day-to-day of a construction company this distinction works well:
| Type | What it includes | Examples |
|---|---|---|
| Direct | What is consumed on a specific work item | Crew hours on that item, materials installed, a subcontractor for that unit of work |
| Site indirect costs | What is spent on a job but not on a specific work item | Site cabin, fencing, crane, the site foreman, site water and electricity |
| Company overheads | What exists even when there are no jobs running | Office, administration, management, insurance, accountancy advice, shared vehicles, stores |
Site indirect costs can be charged to the job that causes them. The real problem lies in company overheads, which have to be allocated across all your jobs using some criterion.
The most common allocation criteria
In proportion to labour hours
Each job takes a share of the indirect costs based on the hours of in-house staff it has used. This is the most sensible criterion for firms that build with their own workforce, because a large part of the overhead structure exists to organise, move and pay those people.
In proportion to direct cost
The costs are shared out according to the total direct cost of each job. It is simple, but it loads more onto jobs with a lot of materials or subcontracting, even if they have hardly kept the office busy.
In proportion to output
The costs are shared out according to what has been invoiced or certified. It is easy to calculate, but it mixes cost with selling price: a well-priced job ends up paying more overhead than a badly priced one.
Weighted
Several criteria are combined, each with its own weighting, or each group of costs is allocated using the criterion that explains it best: vehicles by journeys, the technical office by hours, the stores by material handled. It takes more work to set up, but it reflects reality better.
A worked example
Suppose, for example, a company with overheads of 12,000 euros a month and three jobs under way:
| Job | Staff hours | % of hours | Indirect costs allocated |
|---|---|---|---|
| Shop refurbishment | 400 | 20 % | €2,400 |
| Warehouse roof | 600 | 30 % | €3,600 |
| Block of flats | 1,000 | 50 % | €6,000 |
| Total | 2,000 | 100 % | €12,000 |
Dividing the overheads by the total hours gives a rate of 6 euros per hour worked. That rate can be added to the cost of each hour on the work reports, so that every report carries its share of overheads without waiting for the month-end close. If the shop refurbishment shows a direct margin of 2,000 euros, it is actually losing 400 euros once its indirect costs are loaded on.
How to calculate the rate and when to review it
- Add up your overheads for the last twelve months, leaving out anything already charged directly to jobs.
- Choose the allocation base (hours, direct cost, output or a combination) and work out its total for the same period.
- Divide and you have your rate: euros per hour, a percentage of direct cost, or whatever suits.
- Use it in your quotes and in cost control, applying the same criterion to both.
- Review it at least once a year, or whenever something significant changes: a new yard, more office staff or a drop in activity.
Bear in mind that if activity falls, the rate goes up: the same costs are spread over fewer hours. That is exactly what you need to keep in mind when quoting in quiet periods.
Common mistakes
- Not allocating them at all. This is the most common mistake and the one that distorts most: every job looks profitable while the company loses money.
- Using an inherited percentage. An overhead percentage set years ago may have nothing to do with your current structure.
- Allocating only at year end. By then you can no longer correct prices or decisions.
- Charging jobs for costs that are not theirs. A vehicle used mainly for sales visits should not be allocated in the same way as one that goes to site every day.
- Forgetting travel. On small, scattered jobs the time spent travelling there and back is a large part of the cost, and it should be spread across the day's jobs.
Indirect costs in Gestrab
Gestrab calculates costs per work report and per job, including everything it really costs to carry the job out: labour based on the hours in each report and the hourly cost, the materials used, indirect costs allocated on a weighted basis, and travel spread across the day's reports. That way each job carries its share of overheads and not just its direct expenses. You can find it under costs per job.
Hours and travel come in from the operatives' app: the time each employee takes the vehicle and the time they arrive are used to spread the costs across the day's reports. You can see it under site work reports from your mobile. And if you want to follow the profitability of your jobs at a glance, the Power BI dashboard shows it alongside the company's other indicators.