A well-researched unit price is worthless if the measurement is wrong. If you measure short, you will build more work than you get paid for; if you measure long, you will lose the bid or have to explain later why you cannot deliver what was quoted. Measurements are the least glamorous part of an estimate and one of the parts that moves the most money. Here are the most common mistakes, how to avoid them and a checklist to run through before you send the quote.

Why measurement matters as much as price

In an estimate broken down by line item, the amount of each line is the quantity multiplied by the price. A 10% error in the quantity has the same effect on the amount as a 10% error in the price, but it is much harder to spot: anyone who knows the market can check a price, whereas a measurement is only checked by someone who measures again.

What is more, on site the measurement counts twice: when you estimate and when you certify. If the one in the estimate bears no resemblance to the real one, every certification will turn into an argument with the client over why an item is above or below what was forecast.

Common measuring mistakes

Measuring from drawings that are not the final ones

It is very common to estimate from one version of the project and build from another. Always note in the estimate which drawings and which date you used. If they change, you will know which items to review and you will have grounds to ask for payment for the new work.

Mixing up the measurement criterion

Measuring along a continuous run is not the same as deducting openings, nor is measuring area in horizontal projection the same as in true size on a pitched roof. Each item must state in its description how it is measured, and whoever measures must apply that criterion and no other. A sloping roof measured on plan can come up noticeably short.

Forgetting ancillary items

Finishing details, overlaps, junctions, forming falls, auxiliary equipment, protection of work already completed or the final clean-up. If they are not in an item of their own or explicitly included in the price of another, nobody gets paid for them.

Wrongly chosen units

A gutter measured in square metres, concrete in square metres instead of cubic metres, or steel in units instead of kilos. It seems trivial, but it is a frequent source of absurd amounts that nobody notices until the invoice arrives.

Copying measurements from a previous job

Reusing a similar estimate saves time, but it carries over measurements that do not apply. If you start from an old quote, measure every item again, even if you keep the structure and the prices.

Always rounding in the same direction

Rounding each item down by a few metres to stay competitive seems harmless. Added up across all the items on a job, it can eat your margin.

Mistakes that appear during execution

  • Concealed work left unmeasured. Fill, repairs or embedded services that are covered over before anyone measures them, leaving no way to justify them afterwards.
  • Overruns not communicated. If an item is going to exceed what was designed, you have to say so before carrying it out, not in the final certification.
  • Out-of-scope work mixed in. New work slipped into an existing item distorts its measurement and its cost.
  • Progress measured by eye. An unsupported "it's 70% done" ends up being corrected downwards in the final measurement.

How to organise your measurements so you don't go wrong

  1. Separate measurement from pricing. First measure all the items using their criteria; then put prices on them. Doing both at once is the easiest way to skip lines.
  2. Leave a trail for every measurement. A measurement line with its description (room, grid line, floor), number of units, length, width and height lets someone else check it.
  3. Get a second pair of eyes. The highest-value items, at the very least, should be measured or reviewed by two people.
  4. Compare ratios. Metres of partition wall per metre of floor area, kilos of steel per cubic metre of concrete, or metres of skirting per metre of flooring. A ratio outside the norm usually hides an error.
  5. Visit the site. In refurbishments and renovations, what you cannot see on the drawings is what deviates most.

Checklist before sending the quote

  • Every item states its unit and its measurement criterion.
  • Measurements are based on the latest version of the drawings, noted in the estimate.
  • Ancillary items (finishing details, auxiliary equipment, clean-up, waste management) are included, or it is expressly stated that they are not.
  • The highest-value items have been reviewed by another person.
  • The main ratios make sense for the type of job.
  • Whatever could not be measured (for example, what turns up during demolition) is outside the fixed price and it is stated how it will be valued.

From estimate to site with Gestrab

In Gestrab every estimate is built by line item, with its measurements, price and amount, and it is printed with your company's design. When the client accepts, the job is generated from that estimate, with no need to re-key the items. You will find it in estimates and jobs.

From there, each item of the job distinguishes between the designed, completed, certified and invoiced quantity. That lets you see straight away which items are falling short or running over compared with what was measured in the estimate, and carry that information into the next bid. You can see the costs of each work report and each job, with the hours and materials coming in from the reports, in costs per job.