Most construction jobs that lose money don't lose it at the end: they lose it bit by bit, item by item, and the problem only shows up when the job is closed and there is nothing left to do about it. Spotting a cost overrun in time means comparing what you planned to spend with what you are actually spending while you can still react. In this article you will find what to compare, how often, and what to do when the numbers don't add up.
What a cost overrun is and why it is spotted late
A cost overrun is the difference between the planned cost of the work completed and the actual cost of that same work. The key is "for the work completed". Comparing cumulative spend with the total budget tells you nothing: if halfway through the job you have spent 50% of the planned cost, everything may be fine or it may be going very badly, depending on how much work has really been done.
It is spotted late for three common reasons:
- Costs arrive late: the supplier's invoice comes in weeks after the material has been installed.
- The crew's hours are jotted down on paper and written up when someone has time, or are not assigned to any job.
- Progress is measured for certification, not for cost control, and sometimes using different criteria.
The three figures you need to compare
For each item, or at least for each chapter, you need three figures at the same date:
| Figure | What it is | Where it comes from |
|---|---|---|
| Planned cost of work completed | What the work done to date should have cost | Quantity completed multiplied by the unit cost planned in the estimate |
| Actual cost of work completed | What it has really cost | Hours, materials, machinery, subcontractors and travel charged to the job |
| Output | What the work completed is worth at selling price | Quantity completed multiplied by the budget price |
If the actual cost exceeds the planned cost for the work completed, you have an overrun. If, in addition, the output does not cover the actual cost, that item is already making a loss. For example, if you have completed 40% of a tiling item and the planned cost of that 40% was 4,000 euros, but you have charged 5,200, the item is overrunning by 30%. Waiting until it is finished to see this means waiting for the overrun to multiply.
Warning signs you can check every week
- Hours per unit. If a crew takes more hours per metre than estimated, labour will overrun even if nobody has yet recorded it as a cost.
- Material consumption per unit. More material used than planned usually points to breakages, badly calculated offcuts, theft or under-measured quantities in the budget.
- Work reports with no job assigned. Hours that are not charged to any job make every job look more profitable than it is.
- Purchases with no job. The same goes for material: if it isn't assigned, the cost disappears from the job that used it.
- Unbudgeted work. Small extras that the client asks for "while you're at it" and that nobody prices.
- Travel and waiting time. Extra trips to the warehouse or days when the crew waits for another trade.
How often to review and who does it
You don't need a full close every week. What works in many companies is a two-level check:
- Weekly, by the site manager: hours per item, material used and actual progress. Ten minutes per job if the data is already loaded.
- Monthly, with the certification: actual cost charged against certified output, item by item and in total, with the margin that remains.
The monthly review fits naturally with certification: you already have the work completed measured, so all you need is the cost of that same work at the same date.
What to do when an overrun appears
- Check that it is real. Sometimes progress has been measured wrongly or a cost from another job has been charged to this one.
- Find the cause. Crew productivity, purchase price, material waste, client changes or an under-measured quantity in the budget.
- Separate what can be recovered from what can't. If it is work outside the budget, it is priced and presented to the client. If it is your own mistake, you absorb it and correct course for the remainder.
- Adjust the forecast for what is left. Recalculate the expected final cost of the job, not just that of the work completed.
- Note it down for the next estimate. If a productivity rate or a price was wrong, the next bid shouldn't repeat it.
Common mistakes when controlling costs
- Controlling only the job total and not the individual items, so that losses on some are masked by gains on others.
- Forgetting indirect costs and travel, which on small jobs can be a large share of the cost.
- Using an hourly cost that doesn't include employer social security contributions.
- Comparing against the selling budget instead of the planned cost.
- Keeping costs in one place and progress in another, and reconciling them by hand when it is already too late.
How Gestrab helps
In Gestrab, costs are calculated for each work report and for each job: labour based on the hours in each report and the hourly cost, materials used, indirect costs charged on a weighted basis, and travel spread across the day's reports. Each purchase can be assigned to its job, and machinery costs are also charged. It is explained in job costing.
Because work reports are completed from a mobile phone on site, hours and materials arrive the same day rather than at the end of the month. And because each item shows what was planned, completed, certified and invoiced, you can set cost alongside real progress and see which job is making money and which is losing it while there is still time. Progress is tracked from the job itself, as explained in certifications and cumulative invoicing.